fbpx Foothill Gold Line extension updates - Hey SoCal. Change is our intention.
The Votes Are In!
2024 Readers' Choice is back, bigger and better than ever!
View Winners →
Vote for your favorite business!
2024 Readers' Choice is back, bigger and better than ever!
Start voting →
Subscribeto our newsletter to stay informed
  • Enter your phone number to be notified if you win
  • This field is for validation purposes and should be left unchanged.

Home / Neighborhood / San Gabriel Valley / Arcadia Weekly / Foothill Gold Line extension updates

Foothill Gold Line extension updates

by
share with

The design-build team, Foothill Transit Constructors (FTC), is on schedule to have the project’s design work substantially complete next month. The majority of the nearly 100 design packages have been “Approved for Construction,” and the remaining packages are nearing 100% design.
Significant construction is now well underway throughout the corridor. Bridge construction, utility relocation, grade crossing work, and even station construction can be seen at different points along the 11.5-miles.
Some of these activities require street closures and other impactful activities. Stay updated and don’t get surprised by construction!
Utility relocation and mass grading is happening along the entire city of Azusa corridor, and the FTC team broke ground on the first major at-grade crossing in the city yesterday. Dalton Avenue will be closed for approximately six weeks to complete the crossing improvements. Click here to view the construction notice.
Additionally, to accommodate one freight track and two light rail tracks in the future, nine bridges at three crossings are also under construction in Azusa. Palm Drive is closed to thru-traffic for bridge work until May, and Foothill Boulevard has been reduced to one lane in each direction at the bridge crossing until September. Above is a photo of work on the bridge abutments at Citrus Ave.
The Duarte station is the first of six new stations to break ground, and work continues on the nearby Highland Avenue crossing until early March. (Duarte station-work is shown below).
Demolition of the old bridge abutments at Colorado Blvd. in Arcadia is now complete, and work is underway on construction of the new dual-track bridge over this heavily-used street in the city. Colorado Blvd remains closed to thru-traffic until mid-April.
Mass grading is now complete for the 24-acre, $160 million Gold Line Operations Campus in Monrovia. FTC crews are now focused on utility relocation and foundation work on the main building. Utility relocation on streets surrounding the campus is also on-going.
Arcadia: 400 N Santa Anita Ave, Suite 101-B, Arcadia, CA 91006 (Northeast corner of Santa Anita Ave. and La Porte St.) Hours: Mondays and Wednesdays ONLY: 8 a.m. – 4 p.m.
Monrovia: 406 E. Huntington Drive, Suite 202, Monrovia, CA 91016 (Construction Authority Offices) Hours: Mondays through Friday: 8 a.m. – 5 p.m.
Azusa: 1300 W. Optical Drive, Suite 500, Azusa, CA 91702 Hours: Mondays through Friday: 8 a.m. – 5 p.m. Other Community Resources Include: Other Community Resources Include: 24-hour Community Hotline – (626) 324-7098. Construction Authority’s Construction Updates webpage – http://www.foothillextension.org/construction_phases/construction-updates/

More from Arcadia Weekly

Skip to content